How Much Does It Cost to Put a Mobile Home on Land in Phoenix, AZ? [2025 Full Breakdown]

Cost of Putting a Mobile Home on Land in Phoenix, AZ

On average, homeowners can expect to pay between $18,000 and $45,000 for the full site preparation and setup process — excluding the cost of the home itself. This figure covers essential steps like grading, leveling, tie-down system installation, utility hookups, and permits—often coordinated by experienced mobile home contractors in Phoenix who handle every aspect from zoning to final inspection.

Mobile home relocation and setup service in Queen Creek, Arizona with full leveling and tie-downs

How Much Does Land Cost in Phoenix, AZ?

Land acquisition is your first major cost. In Phoenix and nearby areas, raw land prices vary a lot. You might find parcels between $25,000 and $100,000, depending on the location, size, and zoning.

Areas inside city limits often cost more than rural land in Maricopa County. For example, urban lots near public services can be priced above $75,000 per acre. On the other hand, land outside the city might cost as low as $15,000–$30,000 per acre but require more development work.

What Zoning Codes Allow Mobile Homes?

Zoning laws determine whether a mobile home is allowed on a specific property. In Phoenix, mobile homes are usually permitted in R-5, MH, or RU zoning categories. Before you buy, always verify the land’s zoning with:

  • City of Phoenix Zoning Ordinance Lookup
  • Maricopa County Planning & Development

Some lots are part of HOA communities, where mobile homes may not be allowed. Make sure to ask the seller and check for deed restrictions.

If your land isn’t zoned for mobile homes, you’ll need to apply for a zoning change or variance, which can cost $500 to $2,500 and take several months.

Leasing vs Buying Land

If you’re not ready to buy land, leasing is an option. Many mobile home parks in the Phoenix area lease lots for $400 to $800 per month. These parks may include utilities and shared amenities, which reduces setup costs.

However, leased land limits your ownership. You must follow park rules and cannot build permanent additions in most cases.

Preparing for the Next Steps

Once you have land, the next costs include site preparation, foundation work, and permit applications. These steps are necessary before any home can be delivered or installed.

What Does It Cost to Prepare Land for a Mobile Home?

Site preparation is a required step before installing your mobile home. It ensures that the land is level, accessible, and safe for permanent housing. In Phoenix and surrounding desert areas, the land may need special grading or compaction due to soil type or slope.

Given Arizona’s sandy soils and occasional rocky patches, bringing in expert mobile home leveling services ensures your pad is properly leveled and stable for long-term durability.

Here are common site prep costs:

  • Land clearing: $1,500 to $3,500 (removing brush, debris, small trees)
  • Grading and leveling: $2,000 to $5,000
  • Soil testing: $300 to $800 (especially near wash zones or rocky terrain)
  • Driveway access: $1,200 to $3,000 depending on materials

Some areas near Phoenix may also require erosion control or retaining walls due to water runoff issues. If your lot is in a flood-prone area, extra work may be required to elevate the pad or reroute drainage.

Foundation Types and Costs

Foundation requirements vary based on county and home type. In Arizona, especially under HUD standards, most mobile homes must be placed on a permanent foundation. There are three common types:

  1. Concrete slab: $4,500 to $8,000 (flat areas, standard for double-wides)
  2. Pier and beam system: $3,000 to $6,000 (for uneven ground)
  3. Crawl space foundation: $7,000 to $12,000 (less common but used in higher-end mobile homes)

Local codes may also require anchoring systems, known as tie-downs, which add $800 to $2,000. These protect homes from strong desert winds and meet HUD safety standards.

Local codes may also require anchoring systems, commonly known as tie-downs, to meet HUD safety standards. Certified mobile home tie-down services can handle installation and inspection to ensure compliance.

Permits You’ll Need in Phoenix

To install a mobile home legally, you must apply for multiple permits. This process involves inspections and approvals from city or county officials.

Common permits and fees include:

  • Manufactured home installation permit: $300–$800
  • Building or grading permit: $200–$1,000 depending on work
  • Electrical, plumbing, and mechanical permits: $100–$500 each
  • Septic system permit (if off-grid): $600–$1,200

Check the City of Phoenix Planning and Development Services for updated permit forms and zoning maps.

If the home is located outside Phoenix city limits, refer to the Maricopa County Environmental Services for septic and utility permits.

Timeline for Permits and Inspections

Getting permits can take 2 to 8 weeks, depending on your land’s zoning status and paperwork accuracy. After approval, the city or county will schedule inspections to verify:

  • Site grading is complete
  • Foundation meets specs
  • Utility hookups are code-compliant

How Much Does It Cost to Connect Utilities?

Once your foundation is in place, your mobile home needs utility connections. In Phoenix, this includes water, sewer or septic, electricity, and sometimes natural gas.

Water and Sewer Hookups

If your land is near a public water main, the hookup may cost $1,500 to $5,000. If it’s farther away, you’ll pay more for trenching or extending lines.

For sewer, expect:

  • Public sewer connection: $2,000 to $6,000
  • New septic system: $4,000 to $8,000 depending on tank size and soil quality

In rural areas, installing a private well costs $5,000 to $12,000, depending on water table depth.

Electrical Setup

Electric service costs vary based on how close your land is to an existing power grid. Most homeowners pay $1,500 to $3,000 for service drops, poles, or trenching.

Some remote areas may need:

  • New transformer: $3,000 to $5,000
  • Solar alternatives: $10,000 and up (not including battery storage)

Arizona Public Service (APS) or Salt River Project (SRP) are the primary electric utilities in the region. You can explore utility service zones through their sites:

  • APS Service Map
  • SRP Residential Services

How Much Does It Cost to Deliver a Mobile Home?

Delivery charges depend on distance, home size, and access conditions.

Typical costs:

  • Single-wide: $2,000 to $5,000 within Arizona
  • Double-wide: $3,000 to $7,000
  • Setup on site: $1,500 to $3,500 (includes blocking, leveling, tie-downs)

Most companies bundle transport and setup, but confirm what’s included. Narrow roads, steep terrain, or soft sand can increase the price. Ask if escort vehicles or permits are needed.

Final Inspection and Move-In

After installation, inspectors will review:

  • Anchoring and leveling
  • Utility safety
  • Permits and code compliance

If everything passes, you’ll receive a Certificate of Occupancy, allowing legal residence.

Optional Upgrades and Finishing Costs

To finish your home, you may also pay for:

  • Skirting: $500 to $1,500
  • Deck or steps: $1,000 to $2,500
  • Driveway paving: $2,000 to $5,000

These aren’t required but often necessary for appearance, safety, and financing.

Summary: What’s the Total Cost?

The full cost of placing a mobile home on land in Phoenix includes multiple components. Here’s an average range to expect:

CategoryEstimated Cost (USD)
Land purchase$25,000 – $100,000+
Site preparation$3,000 – $8,000
Foundation installation$4,500 – $12,000
Permits and fees$1,000 – $3,500
Utility hookups$4,000 – $15,000+
Delivery and setup$3,000 – $8,000
Optional upgrades$1,500 – $5,000

Estimated Total: $41,000 to $150,000+

Your total depends on the land’s location, condition, utility access, and home size. Costs can be much lower if you already own land or lease space in a mobile home park.

FAQs

Can I put a mobile home on any land in Phoenix?

No. The land must be zoned to allow mobile or manufactured homes. You’ll need to verify zoning with city or county offices.

Is it cheaper to live in a mobile home on land?

Yes, in many cases. Compared to traditional homes, mobile homes can cost less to buy and install. However, land development and hookup costs can add up quickly.

How long does the whole process take?

From land purchase to move-in, expect 2 to 6 months, depending on permits and construction delays.

Do I need a real estate agent or lawyer?

Not always, but it helps. Professionals can check zoning, review contracts, and guide financing or title transfers.